Skip to main content Go to search Jump to main navigation

paulimot builds

Due to the strong growth of paulimot in recent years, our headquarters at Zeppelinstraße 3 has become too small. After acquiring the neighbouring property at Zeppelinstrasse 5/3 with an existing building in March 2019 and the neighbouring property at Zeppelinstrasse 7 with two other existing buildings in July 2020, we are currently undergoing extensive construction and renovation work.

A spacious new building is currently being realised to connect the buildings at Zeppelinstrasse 3 and Zeppelinstrasse 5/3, as well as extensive conversion and extension work in the existing buildings at Zeppelinstrasse 3 and 5/3. Following the departure of the current tenant from the buildings at Zeppelinstrasse 7, conversion work will also be carried out in these properties and a structural connection to Zeppelinstrasse 5/3 will be created.

After renovation work had already been carried out in the existing building at Zeppelinstrasse 5/3 since the second half of 2019, an important milestone was reached on 14 September 2020 after one and a half years of planning: The construction company arrived and started work on our new building. On this page, we will keep you up to date with pictures and current information on our entire new building and extension project.

Dark construction site thumbnail with red lettering "paulimot baut - Zeitraffer", white date "14.09.2020 - 12.10.2021" and red play button.

Project schedule

  • Since January 2019
  • Planning of the overall project and in particular the new building
  • May 2019 until January 2020
  • Renovation of the upper floor (offices) of the existing building Zeppelinstraße 5/3
  • September 2020 until the beginning of 2022
  • Construction and interior fit-out of the new building
  • Mid 2021 until spring 2022
  • Conversion of the ground floor of Zeppelinstraße 5/3 into a reception and meeting area
A 3D sketch of a building complex with red roofs and white walls. The buildings are arranged at an angle and connected by corridors. Shadows indicate a light source from the top right.
  • Beginning of 2022 to mid-2022
  • Remodelling of the existing building at Zeppelinstraße 3, installation of additional office space
  • Spring and summer 2022
  • Construction of a connecting corridor to Zeppelinstraße 7 and redesign of the outdoor facilities
  • From spring 2022
  • Comprehensive reorganisation of the technology and logistics divisions
  • From autumn 2022
  • Remodelling work in the buildings at Zeppelinstraße 7
Ground-breaking ceremony

Image 1: The Paulitschek family at the ground-breaking ceremony for the new building (17 September 2020).

Image 2: The ground-breaking ceremony marks the next milestone for the new building (17 September 2020).

Excavation pit and construction crane

Image 1: View from Zeppelinstraße 3 towards Zeppelinstraße 5/3 of the construction site for the future connecting building (11 September 2020).

Image 2: The construction site is cleared in preparation for the excavation work (15 September 2020)

Image 3: The excavation work has begun (18 September 2020)

Image 4: The excavation pit is almost completely excavated (23 September 2020)

Image 5: The construction crane is being erected... (30 September 2020)

Image 6: ... and towers above the existing buildings on the same evening (30 September 2020).

Basement walls

Image 1: Things are now progressing quickly: the first basement walls have been concreted and a connection to the existing building at Zeppelinstrasse 5/3 is being created in the basement (12 November 2020).

Image 2: The existing building at Zeppelinstrasse 3 from a perspective we have not seen before (12 November 2020).

Image 3: Almost all the basement walls are finished, the stairwell and lift shaft are visible (18 November 2020).

Basement ceiling

Image 1: The formwork for the basement ceiling is being erected (24 November 2020)

Image 2: A forest of columns spreads out in the basement (27 November 2020).

Image 3: The slab formwork is fully erected and the reinforcement work is almost complete (14 December 2020)

Image 4: Concreting work on the basement ceiling begins in the early morning darkness... (16 December 2020).

Image 5: ... and continue smoothing into the next night (16 December 2020).

Ground floor

Image 1: After a long winter break due to the weather, work continues on the ground floor walls (5 February 2021).

Image 2: View from the east with connection to the existing building at Zeppelinstraße 5/3 (17 February 2021).

Image 3: The walls for the ground floor are rising (17 February 2021).

Image 4: Colourful mix of concrete and bricks (24 February 2021).

Ceiling above ground floor

Image 1: The formwork for the ceiling above the ground floor is being erected... (26 February 2021)

Image 2: ... and once again allows new insights and views (1 March 2021).

Image 3: The reinforcement work is progressing (3 March 2021)

Image 4: The ceiling above the ground floor is concreted (8 March 2021).

Upper floor

Image 1: The scaffolding and the first walls are going up (10 March 2021).

Image 2: The walls for the connection to the Zeppelinstraße 3 building are being built (17 March 2021).

Image 3: Concrete columns in the snow flurry (19 March 2021).

Image 4: The windows of the future offices are already clearly visible (with a little imagination) (22 March 2021)

Image 5: Every new floor also needs a staircase (29 March 2021).

Ceiling above upper floor

Image 1: The formwork for the ceiling above the upper floor - which is also the building roof - is being erected (24 March 2021).

Image 2: The reinforcement for the building roof is in place (7 April 2021).

Image 3: Heavy equipment moves in one last time for concreting the ceiling above the upper floor (7 April 2021).

Image 4: Even the top of Ulm Minster can be seen from the roof (7 April 2021)

Image 5: The roof is topped off with a parapet (12 April 2021).

Renovation of Zeppelinstraße 5/3 (part 1)

Image 1: The installation of a reception and meeting area in the Zeppelinstraße 5/3 building begins with demolition work (26 March 2021).

Image 2: The first partition walls are bricked and the installation work for the new sanitary area begins (16 April 2021)

Image 3: Drywall construction is progressing (21 April 2021).

Image 4: The installation of the underfloor heating is being prepared... (30 April 2021)

Image 5: ... and a few weeks later the screed is installed (26 May 2021).

New build: Roof waterproofing and windows

Image 1: The roof is waiting for the roofer (9 May 2021).

Image 2: The first layer of bitumen sheeting is laid and welded (21 May 2021).

Image 3: The window fitters begin installing the windows and glass façade at the same time as the roofers (31 May 2021).

Image 4: The façade takes shape... (2 June 2021)

Image 5: ... and the roof has now received the sloping insulation and a further bitumen sealing layer (9 June 2021).

New building: Interior work (part 1)

Image 1: Interior work also begins in the new building (14 June 2021).

Image 2: The first drywall walls can be seen on the upper floor - the future office floor (16 June 2021).

Image 3: A new sanitary area is also being built in the new building (18 June 2021)

Image 4: The corridor and future offices are now clearly distinguishable (21 June 2021).

New building: Plastering work

Image 1: At the same time as the interior work on the upper floor began, the plasterers started work on the exterior walls on the south and west façades... (25 June 2021)

Image 2: ... and on the north side of the new building (28 June 2021).

Image 3: The future storage and assembly area on the ground floor receives the first layer of lime-cement plaster (2 July 2021)

New building: Technical building services (part 1)

Image 1: Insulation and dimpled sheets are installed in the future office and meeting rooms on the upper floor, ... (7 July 2021)

Image 2: ... on which the heating loops for the underfloor heating will then be laid (19 July 2021)

Image 3: Installation of the heating system also begins in the future assembly hall (23 July 2021)

Image 4: More and more cable and installation routes are visible under the ceilings (9 August 2021).

Image 5: After the tradesmen's holidays, the technical installations on the ground floor and basement are largely complete (29 September 2021).

New building: Interior work (part 2)

Image 1: The screed is installed on the upper floor (26 July 2021)

Image 2: Installation of the lift begins... (12 October 2021)

Image 3: ... and is completed a few days later (15 October 2021).

Further exterior views

Image 1: View of the new and existing buildings at Zeppelinstrasse 5/3 from the east (9 August 2021).

Image 2: The north façade is slowly revealing its final appearance (20 October 2021)

Image 3: The balcony on the north side is only missing the floor covering (3 November 2021)

Image 4: For the first time, the new building appears without scaffolding - here the west and part of the south façade (8 November 2021)

Image 5: The infiltration trench for rainwater is installed (12 November 2021).

New building: Technical building equipment (part 2)

Image 1: The technical installations on the upper floor are progressing (15 October 2021).

Image 2: The cooling and ventilation systems are largely installed (15 October 2021)

Image 3: The electrical engineering is also making progress - although there is obviously still some work to be done here (15 October 2021).

New building: Interior fit-out (part 3)

Image 1: Installation of the suspended ceilings begins in the first offices (29 October 2021).

Image 2: The first acoustic ceilings are installed (8 November 2021)

Image 3: The tiler has started work in the corridors on the upper floor (19 November 2021)

Image 4: The old tiles in the existing building at Zeppelinstraße 5/3 have to make way for a uniform look in future (24 November 2021).

Image 5: Installation of the interior glass systems has begun (26 November 2021).

New building: Interior work (part 4)

Image 1: Drywall construction is progressing in the corridors (3 December 2021).

Image 2: White paint and wallpaper make the ceilings and walls really stand out (6 December 2021)

Image 3: The drywall construction and painting work has been completed in the first offices (8 December 2021)

Image 4: The carpet and lights make it look much cosier (15 December 2021).

Image 5: The furniture finally completes the picture (17 December 2021).

Facts about the new building

1,700 m²New warehouse space
750 m²New office space
2,800 m²Total warehouse space after conversion
1,100 m²Total office space after conversion
Approx. 1,850 m²Removal of soil and gravel
approx. 1,800 m²use of concrete
approx. 65,000 kguse of steel
57New office workplaces
100,000New grey hairs since start of construction
76Total office workplaces after remodelling

We thank our partners for the trustful co-operation...

Planning
Architecture Dipl.-Ing. (FH) Raimund Stolz, Lonsee-Luizhausen
Structural engineering Engineering office Hausmann and Walk, Ulm
Structural analysis LGA Landesgewerbeanstalt Bayern Corporation under public law, Augsburg
TGA planning INUTEC Engineering & Management GmbH, Ulm
Interior design Dipl.-Ing. (FH) Gabriele Ziegler, Wolfertschwenden
Fire protection Dr Kathrin Grewolls, Ulm
Health and safety coordinator Dipl.-Ing. (FH) Beate Jansen, Neu-Ulm
Surveying Dipl.-Ing. (FH) Arnfried Wollschlaeger, Lonsee
Drainage planning Deißler engineering office, Dornstadt
Geotechnics Schirmer Ingenieurgesellschaft mbH, Ulm
Building physics Dipl.-Bauingenieur (FH) Paul Betz, Griesingen

Building envelope and outdoor facilities
Earthworks and structural work Christoph Haide GmbH & Co KG, Langenau
Waterproofing work Roland Wolf GmbH, Erbach
Building drying TROWA Wallisch GmbH, Langenau
Roofing work Dittmar GmbH, Neu-Ulm
Tinsmith work Josef Stahl GmbH, Neu-Ulm
Fixed ladders MUNK GmbH, Günzburg
Glass façade and windows Kräss GlasCon GmbH, Neu-Ulm
Gates and exterior doors BFB Pernes, Berghülen
Glass roofing atrium Kräss GlasCon GmbH, Neu-Ulm
Vestibule Kräss ClasCon GmbH, Neu-Ulm
Exterior plaster Hampel GmbH, Elchingen
Paving work Markus Brugger KG, Vöhringen
Gardening and landscaping Contract award not yet finalised

Technical trades
Heating and sanitary installations Josef Stahl GmbH, Neu-Ulm
Electrical installations Reimer Elektrotechnik GmbH & Co KG, Neu-Ulm
Refrigeration technology KKI GmbH & Co KG, Buch
Ventilation technology Heizbär & Eisbär GmbH, Buch
Lift Hydraulic Lift Systems Walter Mayer GmbH, Bruchsal
Integrated lifting platforms Willecke Hebe- und Fördergeräte GmbH, Hattingen

Would you like to find out more about our team?

We introduce all paulimot employees on our team page. Take a look and get to know us better.

To the "Team paulimot"

Would you like more information about paulimot?

Then sign up for our newsletter! Exciting news is waiting for you.

To the registration